CFP last date
20 January 2025
Reseach Article

Three Phase Fault Currents Evaluation for 11 Bus 132 kV Transmission System, kotkapura

Published on September 2016 by Kuljinder Kaur, Simerpreet Singh
International Conference on Advances in Emerging Technology
Foundation of Computer Science USA
ICAET2016 - Number 10
September 2016
Authors: Kuljinder Kaur, Simerpreet Singh
a30a385a-d129-4015-81fc-d699a2f7a2d8

Kuljinder Kaur, Simerpreet Singh . Three Phase Fault Currents Evaluation for 11 Bus 132 kV Transmission System, kotkapura. International Conference on Advances in Emerging Technology. ICAET2016, 10 (September 2016), 13-17.

@article{
author = { Kuljinder Kaur, Simerpreet Singh },
title = { Three Phase Fault Currents Evaluation for 11 Bus 132 kV Transmission System, kotkapura },
journal = { International Conference on Advances in Emerging Technology },
issue_date = { September 2016 },
volume = { ICAET2016 },
number = { 10 },
month = { September },
year = { 2016 },
issn = 0975-8887,
pages = { 13-17 },
numpages = 5,
url = { /proceedings/icaet2016/number10/25941-t156/ },
publisher = {Foundation of Computer Science (FCS), NY, USA},
address = {New York, USA}
}
%0 Proceeding Article
%1 International Conference on Advances in Emerging Technology
%A Kuljinder Kaur
%A Simerpreet Singh
%T Three Phase Fault Currents Evaluation for 11 Bus 132 kV Transmission System, kotkapura
%J International Conference on Advances in Emerging Technology
%@ 0975-8887
%V ICAET2016
%N 10
%P 13-17
%D 2016
%I International Journal of Computer Applications
Abstract

Modern power system is very complex in nature, having number of buses, transmission lines, which increases the complexity of power system and fault level of power system increases to large extent. Fault studies are important power system analysis for stable and economical operations of power systems. In this paper, short circuit analysis was performed on three phase balanced fault using 132 kV transmission system model in Power World Simulator. Load flow studies were performed which determined pre-fault conditions for the power system based on Newton- Raphson method. Further, voltage and current magnitudes were determined by imposing three phase balanced fault on the system for rated current of 400 and 630 Amp. The information gained from the analysis can be used for proper relay selection, settings, performances and coordination.

References
  1. Bhadauria, S. and Doad, K. S. , (2014) "Numerical Techniques for Bus Bar Protection", International Journal of Engineering Research and Applications (IJERA), Vol. 152, 6, pp 82-85.
  2. Castellanos, F. and Dillah, R. , (2008) "Short Circuit Analysis in the Phase Domain for Distribution Networks", Transmission & distribution conference, IEEE, pp 1-6.
  3. Cintula, B. , Eleschova, Z. and Belan, A. , (2007) "3-Phase Short Circuit Impact in Various Length of Power Line on Transient Stability of Synchronous Generator", Recent advances in energy, environment & economic development.
  4. Debniloy, D. , Mishra, S. A. , Kar, A. and Mahapatra, S. (2014) "Short Circuit Analysis of a Power Grid using MiPower Software", Advance in Electronic and Electric Engineering, Vol. 4, 3, pp. 253-258.
  5. Durocher, D. B. (2011) "Understanding Circuit Breaker Design and Operation to Improve Safety and Reliability in Underground Mining".
  6. Filipovi-Gri, B. , Uglesi, I. and Filipovi-Gri, D. , (2011) "Analysis of Transient Recovery Voltage in 400 kV SF6 Circuit Breaker Due to Transmission Line Faults", International Review of Electrical Engineering, Vol. 6, pp 2652-2658.
  7. Filomena, A. D. , Resener, M. , Salim, R. H. and Bretas, A. S. , (2011) "Distribution Systems Fault Analysis considering Fault Resistance Estimation", International journal of Electrical Power and Energy Systems, Vol. 33, pp 1326-1335.
  8. Kakilli, A. , (2013) "System Analysis with the Mva Method for Symmetrical Three-Phase Faults", Marmara University Technical Education Faculty, Istanbul, Turkey.
  9. Meyer, C. , Kollensperger, P. and Doncker, R. W. D. , (2004) "Design of a Novel Low Loss Fault Current Limiter for Medium-Voltage Systems".
  10. Roybal, D. D. (2004), "circuit Breaker Interrupting Capacity and Short-Time Current Ratings", IEEE IAS Pulp and Paper Industry Conference, pp 130-134.
  11. Sen, S. , Chatterjee, A. and Sarkar, D. , (2013) "Design of 132/33KV Substation", International Journal of Computational Engineering Research, Vol. 03, 7.
  12. Shah, S. G. and Bhasme, N. R. , (2014) "Design of Earthing System for HV/EHV AC Substation", International Journal of Advances in Engineering & Technology, Vol. 6, 6, pp. 2597-2605.
  13. Shrivastava, P. , Modi, S. S. and Shrivastava, P. , (2014) "Short Circuit Analysis by Using Mi-Power", International Conference On Emerging Trends in Mechanical and Electrical Engineering.
  14. Tziouvaras, D. , (2003) "Analysis of Complex Power System Faults and Operating Conditions", IEEE Transactions on Power Delivery, Vol. 12, 1, pp. 134-143
  15. Yu, X. and Singh, C. , (2002) "Power System Reliability Analysis Considering Protection Failures". .
Index Terms

Computer Science
Information Sciences

Keywords

Power System Power Flow Three-phase Fault Short- Circuit Current.