Schedule Risk Analysis of ICT Infrastructure Projects

by Malaya Kumar Nayak, Dr Sanghamitra Mohanty
International Journal of Computer Applications
Foundation of Computer Science (FCS), NY, USA
Volume 38 - Number 5
Year of Publication: 2012
Authors: Malaya Kumar Nayak, Dr Sanghamitra Mohanty
10.5120/4681-6803

Malaya Kumar Nayak, Dr Sanghamitra Mohanty . Schedule Risk Analysis of ICT Infrastructure Projects. International Journal of Computer Applications. 38, 5 ( January 2012), 1-5. DOI=10.5120/4681-6803

@article{ 10.5120/4681-6803,
author = { Malaya Kumar Nayak, Dr Sanghamitra Mohanty },
title = { Schedule Risk Analysis of ICT Infrastructure Projects },
journal = { International Journal of Computer Applications },
issue_date = { January 2012 },
volume = { 38 },
number = { 5 },
month = { January },
year = { 2012 },
issn = { 0975-8887 },
pages = { 1-5 },
numpages = {9},
url = { https://ijcaonline.org/archives/volume38/number5/4681-6803/ },
doi = { 10.5120/4681-6803 },
publisher = {Foundation of Computer Science (FCS), NY, USA},
address = {New York, USA}
}
%0 Journal Article
%1 2024-02-06T20:24:43.938953+05:30
%A Malaya Kumar Nayak
%A Dr Sanghamitra Mohanty
%T Schedule Risk Analysis of ICT Infrastructure Projects
%J International Journal of Computer Applications
%@ 0975-8887
%V 38
%N 5
%P 1-5
%D 2012
%I Foundation of Computer Science (FCS), NY, USA
Abstract

Scheduling a project is an inexact process in that it tries to predict the future. An ICT infrastructure project is a combination of interrelated activities that must be performed in a certain order of completion. To cut development costs and meet tight deadlines in ICT software Infrastructure Projects, managers need to understand some key doubts about the standard scheduling methods and how to use a schedule risk analysis to provide information crucial to an ICT Infrastructure Project's success before they embark on their ICT Infrastructure Project. This study deals with the benefit of conducting schedule risk analysis on an ICT Infrastructure Project. It is shown that such risk analysis has the potential to provide key information for ICT Infrastructure project managers in advance so that risk mitigation plans can be developed and implemented in time.

References
  1. Abdel-Hamid, T. and Madnick, S., 1991. Software Project Dynamics, An Integrated Approach, Prentice Hall, Englewood Cliffs, New Jersey.
  2. AS/NZS 4360, 2004. Australian Standard: Risk Management, Standards Australia
  3. Banks, J., Carson, J. S., II, and Nelson, B. L., 1996. Discrete-Event System Simulation, second edition, Prentice Hall.
  4. Bannerman, P. L., 2008. ‘Risk and risk management in software projects: A reassessment’, Journal of Systems and Software, Vol. 81, No. 12, pp. 2118–2133.
  5. Bratley, P., Fox, B. L., and Schrage, L. E., 1987. A Guide to Simulation, second edition, Springer-Verlag.
  6. Deepti, V., Ramanamurthy, N., and Balasubramanian, K. U., 2004. ‘Effective risk management: risk analysis using an enhanced FMEA technique’. Proc. of Annual Project Management Leadership Conference, India.
  7. Fishwick, P. A., 1995. Simulation Model Design and Execution: Building Digital Worlds, Prentice-Hall.
  8. Freund, J. E., 1992. Mathematical Statistics, fifth edition, Prentice-Hall.
  9. Gogg, T. and Mott, J., 1992. Improve Quality and Productivity with Simulation, Palos Verdes Pnsl., CA.
  10. Hogg, R. V., and Craig, A. T., 1995. Introduction to Mathematical Statistics, fifth edition, Prentice-Hall.
  11. Humphrey, W., 1997. Introduction to the Personal Software Process, Addison-Wesley.
  12. Kellner, M. I., Madachy, R. J., and Raffo, D. M., 1999. ‘Software process simulation modeling: Why? What? How?’ Journal of Systems and Software, Vol. 46, pp. 91–105.
  13. Kelley, J. E. and Walker, M. R., 1959. ‘Critical-path planning and scheduling’, Paper Presented at the Eastern Joint IRE-AIEE-ACM Computer Conference, ACM New York, NY, USA, December 1–3.
  14. Kerzner, H., 2009. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, John Wiley and Sons.
  15. Kleijnen, J. P. C., 1987. Statistical Tools for Simulation Practitioners, Marcel Dekker, New York.
  16. Misra, S. C., Kumar V., and Kumar, U., 2005. ‘Modeling strategic actor relationships to support risk analysis and control in software projects’. Proc. of the 2005 International Conference on Enterprise Information Systems, Miami, Florida, USA, May 25–28, pp. 288–293.
  17. Montgomery, D. C., 1997. Design and Analysis of Experiments, third edition, John Wiley.
  18. Nelson, B. L., 1995. Stochastic Modeling: Analysis and Simulation, McGraw-Hill.
  19. Neumann, P. G., 1994. Computer-Related Risks, Addison-Wesley.
  20. Rodrigues, A., 1996. ‘The role of system dynamics in project management’, International Journal of Project Management, Vol. 14, No. 4, pp. 213–220.
  21. Suri, P. K. and Soni, R., 2007. ‘Simulating the potential effect of risk management on project scheduling’, Information Technology Journal, Vol. 6, No. 1, pp. 8–13.
  22. Tiwana, A., and Keil. M., 2004. ‘The one-minute risk assessment tool’, Communications of the ACM, Vol. 47, No. 11, pp. 73–77.
Index Terms

Computer Science
Information Sciences

Keywords

Risk planning ICT Scheduling Risk Project planning Simulation