Unit based Scheduling in Project Management: A Programming Approach

by D. Anuradha, S. Bhavani
International Journal of Computer Applications
Foundation of Computer Science (FCS), NY, USA
Volume 59 - Number 4
Year of Publication: 2012
Authors: D. Anuradha, S. Bhavani
10.5120/9540-3978

D. Anuradha, S. Bhavani . Unit based Scheduling in Project Management: A Programming Approach. International Journal of Computer Applications. 59, 4 ( December 2012), 49-55. DOI=10.5120/9540-3978

@article{ 10.5120/9540-3978,
author = { D. Anuradha, S. Bhavani },
title = { Unit based Scheduling in Project Management: A Programming Approach },
journal = { International Journal of Computer Applications },
issue_date = { December 2012 },
volume = { 59 },
number = { 4 },
month = { December },
year = { 2012 },
issn = { 0975-8887 },
pages = { 49-55 },
numpages = {9},
url = { https://ijcaonline.org/archives/volume59/number4/9540-3978/ },
doi = { 10.5120/9540-3978 },
publisher = {Foundation of Computer Science (FCS), NY, USA},
address = {New York, USA}
}
%0 Journal Article
%1 2024-02-06T21:05:17.860569+05:30
%A D. Anuradha
%A S. Bhavani
%T Unit based Scheduling in Project Management: A Programming Approach
%J International Journal of Computer Applications
%@ 0975-8887
%V 59
%N 4
%P 49-55
%D 2012
%I Foundation of Computer Science (FCS), NY, USA
Abstract

A unit based scheduling technique is proposed to assess networks of the given project and find out the optimum schedule. The proposed approach uses an iterative method to execute unit expediting and the expedition is done to the desired amount for all activities along the critical path. The output of the proposed approach includes a distribution of the total cost of project, duration of project completion and it is mainly applicable where cost and duration are of major issues. A computer program has also been developed using the C programming language to support the efficiency of the logic applied in the algorithm. A civil construction scheduling has been solved illustrating the validity of the proposed algorithm. This algorithm can serve as an important tool for the project managers to run the projects speedily and successfully.

References
  1. Ameen, D. A. 1987. A computer assisted PERT simulation, J. Syst. Management, 38, pp. 6-9.
  2. Badiru, A. B. 1991. A simulation approach to network analysis, Simulation, 57, pp. 245- 255.
  3. Dishi Xu and Xianggang Hua . 2011. The Applications of Crashing Algorithm in Project Management, IEEE, pp. 349-354.
  4. Feng, C. W. ,L. Liu and S. A. Burns . 2000. Stochastic construction time-cost trade-off analysis, Journal Comput. Civil Engg. , 14, pp. 117-126.
  5. Ghazanfari M, Shahanaghi K, Yousefli K A . 2008. An Application of possibility goal programming to the time-cost trade-off problem, JUS, World academic press, 2, pp. 22-28.
  6. Haga, W. A. , and K. A. Marold . 2004. A simulation approach to the PERT CPM time-cost trade-off problem, Project Management Journal, 35, pp. 31-37.
  7. Haga, W. A. , and K. A. Marold . 2005. Monitoring and control of PERT networks, The Business Review, 3, pp. 240-245.
  8. JIN Chao-guang, JI Zhuo-shang, LINYan Zhao Yuan-min, Zhen-dong . 2005. Research on the fully fuzzy time-cost trade-off based on genetic algorithms, Journal of Marine Science and Application, 4, pp. 18-23.
  9. Michael E. Kuhl . 2008. A dynamic crashing method for project management using simulation based optimization, Proceedings of the 2008 Winter Simulation Conference, pp. 2370-2376.
  10. Pulat, P. S and S. J. Horn . 1996. Time-Resource trade-off problem (project scheduling), IEEE Trans. Eng. Management, 43, pp. 411-417.
  11. Ramini S. 1986. A simulation approach to time-cost trade-off in project network, Modeling and Simulation on Microcomputers, Proceedings of the Conference, pp. 115-120.
  12. Shakeela Sathish and K. Ganesan . 2012. Fully fuzzy time-cost trade-off in a project network- A new approach, Mathematical Theory and Modeling, 2, pp. 53-65.
  13. Yang T . 2007. Impact of budget uncertainty on project time-cost trade-off, Eng Manage, 52, pp. 167-174.
  14. Yassiah Bissiri and Scott Dunbar . 1999. Resource Allocation Model for a Fast-Tracked Project, Intelligent Processing and Manufacturing of Materials, 1, pp. 635-640.
  15. Yousefli K A, Ghazanfari M, Shahanaghi K, Heydari M . 2009. A new heuristic model for fully fuzzy project scheduling, JUS, World academic press, 2, pp. 73-78.
Index Terms

Computer Science
Information Sciences

Keywords

Project Network Critical path Incremental cost Expediting